BC Hydro documented Friday it has “critical problems” about the Web-site C dam venture because of to the impact of COVID-19 and other worries.

In a letter opening a quarterly report to the BC Utilities Fee, BC Hydro President and CEO Chris O’Riley mentioned mainly because of the pandemic, get the job done has been reduced and other problems have led to problems regarding program, scope and spending budget of the undertaking.

On March 18, BC Hydro introduced it was cutting some function on the job in reaction to provincial steps to deal with COVID-19 transmission.

The workforce remaining at the dam internet site in northern B.C. has been scaled back by about 50 per cent to operate connected only to crucial solutions like security and protection, and river diversion, O’Riley said.

Function continued in off-site parts, which includes freeway re-alignment and reservoir cleansing, where physical distancing is less difficult to keep.

On May well 14, BC Hydro introduced it would get started “safely and securely” and step by step growing building at the dam site. 

Prior to the pandemic, O’Riley said the $10-billion challenge remained on agenda for the very first generating device to commence services in late 2023 with a closing in-service day of 2024.

That day is now up in the air, he reported, since get the job done had to be halted during the starting of the pandemic.

BC Hydro examining price tag, timelines

In the letter, O’Riley said the project was now running “sizeable economic pressures” from agreement modification, construction get the job done, labour necessities, 1st Nation treaty infringement claims and an injunction software.

In December 2019, a “venture risk” emerged on the ideal financial institution of the dam website demanding further foundation work. 

On Friday, O’Riley documented those foundation enhancement expenditures are predicted to be “extra considerable than to begin with anticipated.”

Problems about the development of Web-site C were echoed by the minister liable for the challenge.

“I am quite involved by these reports,” Vitality Minister Bruce Ralston reported.

“Particularly as they relate to price tag and timetable uncertainties.”

Ralston mentioned he is appointing former deputy finance minister Peter Milburn to act as a particular advisor on the undertaking.

BC Hydro is reviewing the cost and timelines of the task and suggests it will provide an update in the drop.